Market · Digital infrastructure
Data center siting counsel in France.
Paris has the land, the grid connections and the queue, and it now has an administrative machine that decides which projects get which megawatts. For the general counsel of an operator, a developer or the fund behind one, the practical question is not which firm to instruct in the Eighth. It is who inside the company holds the connection and the permit on the same calendar.
The megawatts are allocated by procedure now, not by queue position alone.
Six lenses on one problem, and each buys a different lawyer. Among the 94 in-house respondents in Sartori's Paris interview cohort holding energy, real-estate or public-law seats, 61 reported over the 24 months to June 2026 that a capacity reservation their company treated as secured was in fact conditional on an authorization no lawyer inside the department was tracking. Anyone shopping for data center siting counsel France is trying to close exactly that hole, and it is a sequencing hole rather than a shortage of expertise.
RTE recorded 770 MW of connection capacity held by dedicated-site data centers at the end of December 2025, mainly in Île-de-France. On its own figures page RTE puts requested power in the region at 6.5 GW, near the region’s average load. Scarcity is now administered.
Each lens is developed below. If you are deciding whether to build the seat or keep instructing outward, start with who holds it today.
- 770 MW
- Connection capacity held by dedicated-site data centersSites of 40 to 240 MW, mainly Ile-de-France, at end-December 2025
- RTE, 2025 Electricity Review, April 2026
- 6.5 GW
- Connection power requested in Ile-de-FranceAgainst a regional average load of about 7 GW
- RTE, Les data centers en chiffres cles, 2026
- 22%
- Average use of connection capacity already grantedTransmission-connected sites, ramping slowly toward nominal load
- RTE, 2025 Electricity Review, April 2026
- 5,000 m²
- Floor area above which Ile-de-France requires a prefectural agrementGuidance reissued 1 June 2026, filings from 1 July 2026
- DRIEAT Ile-de-France fiche repere, 1 June 2026
One region, four measurements, and the temptation to add them.
The opening comparison on this page is a comparison, not a published statistic, and the distinction matters more here than in most markets because the French figures are unusually easy to merge by accident.
In its 2025 Electricity Review, published in April 2026, RTE wrote that the connection capacities of dedicated-site data centers on the public transmission system ranged from 40 to 240 MW and totalled 770 MW at the end of December 2025, adding that these sites are mainly located in Île-de-France. Separately, on the figures page it maintains for 2026, RTE states that requested connection power in Île-de-France stands at 6.5 GW, close to the region’s current average load of about 7 GW. Set one against the other and the gap runs to roughly one to eight. That arithmetic is ours. RTE publishes the two figures; it does not publish the ratio, and the two legs do not measure the same thing.
The first leg measures capacity that has been granted and physically built to. The second measures volume that has been asked for, most of which does not yet exist as steel in a substation. A third figure sits between them: RTE puts capacity reserved in Île-de-France at about 7 GW, with about 6 GW in Hauts-de-France, and reports that by May 2026 it had reserved nearly 18 GW nationally across roughly 80 projects, against about 40 projects and 5 GW at the end of 2024. A fourth belongs to a different industry entirely: the EY and France Datacenter barometer of June 2025 put installed colocation and hyperscale capacity in the Paris market at 683 MW of IT power at the fourth quarter of 2024, against 486 MW a year earlier, and behind London and Frankfurt on the same measure.
Nothing about the French market is legible if those four are averaged. A board paper that reports “Paris has around 700 MW” has said something true about three different quantities and useful about none of them, and the utility will say so. The reason it matters to a legal department is that each figure attaches to a different instrument: granted capacity attaches to a connection convention, requested power to a queue position, reserved capacity to an obligation to keep proving you need it, and installed IT power to a lease.
The gap between granted and drawn is the fact that started the reform. In its 2025 Electricity Review, published in April 2026, RTE put the average rate at which connection capacity is used by transmission-connected facilities at 22 percent, and on its 2026 figures page it reports that sites connected for two to three years draw, on average, only 20 percent of the power they requested. On that same 2026 page RTE records that operators themselves estimate ten to fifteen years to reach about 80 percent of requested consumption. Read charitably, that is the normal physics of filling a building with processors. Read by a regulator with a queue, it is a reason to stop treating a reservation as property.
A number on an applicationElectricity through a meter
- Requested A figure on a connection request. It costs a study, a place in the order of arrival and very little else, which is precisely why the aggregate is so much larger than anything on the ground.
- Reserved Capacity the operator has set aside against a signed engagement. It carries payment obligations, evidence obligations and, since the adjustment rules took effect, an exposure to being reduced if it stays unused.
- Drawn Load actually taken through the connection. The distance between this stop and the previous one is what convinced the regulator to industrialize selection rather than wait for the queue to clear itself.
Granted, installed, requested, reserved. Four measurements, one region, and a board paper that averages them has told the utility it was not read carefully.
Read the requisitions, not the practice pages.
Paris employers do publish what they are hiring for, and the labels are more specific than the market assumes. Across the postings reviewed for this article in 2026, exactly one class of employer puts grid connection on the face of an in-house job description, and it is not the one spending the most money.
A global colocation operator advertised a legal counsel for real estate and infrastructure in Paris on 7 March 2026, hybrid, supporting a growing data center portfolio across France and selected European markets. The requisition names land acquisition and campus development, construction, real-estate portfolio management and, explicitly, energy matters such as grid connection. It asks for real estate, construction, energy or infrastructure experience, strength in two or more of them, and fluency in French and English. It also names the instruction and management of external counsel as a duty of the seat. That is the standing in-house seat this market produces: a lawyer who holds the campus and the connection engagement, and then buys the hearing.
Now read the buyers with the larger budgets. A generative artificial-intelligence platform advertised a senior compute legal counsel in Paris on 28 June 2026, asking for eight or more years and naming compute transactions, procurement, intellectual property, insurance, privacy and export control, with hardware and data center development contracts on the list. It does not mention the connection procedure, the prefectural agrément, the local plan or the administrative courts. An engineering house serving this sector advertised a juriste in Montrouge in December 2025, covering corporate matters and contracts outside projects. A national contractor building campuses across the region was advertising a works manager, not a lawyer at all.
On the other side of the meter the pattern inverts. On the recruitment profile it published in 2026, the transmission operator describes a legal department of roughly seventy people carrying a dedicated pole of nine on network access and electricity markets: connection and access for generators, consumers and distributors, the technical reference documentation behind those procedures, and the negotiation of connection and access contracts. The party that writes the connection paper staffs it internally. The parties that sign it mostly do not, and buy the regulatory slice by the hour.
That asymmetry is defensible while a connection is a commercial negotiation. It stops being defensible once the connection is an administrative procedure with a forfeiture clause, because the decision that has to be made fastest — whether to sign, whether to defend a reservation, whether to abandon a plot — is exactly the decision an external adviser is not permitted to make.
| Buyer | Where the seat sits today | Practice label on the requisition | Who carries the position |
|---|---|---|---|
| Colocation operator | Standing Paris seat inside the legal department | Real estate and infrastructure, with grid connection named on the requisition | Holds the campus and the connection engagement; instructs the hearing |
| Campus developer-operator | Paris corporate legal, entitlements bought outside | Corporate and commercial | External counsel on connection and land use |
| Hyperscale or AI platform | Paris commercial seat; French siting bought outside | Compute and infrastructure contracting, procurement, export control | External counsel on permits and connection |
| Industrial or logistics landlord | Asset-management legal, converting existing holdings | Real estate, construction, change of use | External counsel, late and under schedule pressure |
| Transmission system operator | Dedicated internal pole for network access | Energy regulatory, connection procedures, market rules | Internal; it writes the paper the others sign |
| Infrastructure fund or sponsor | No French siting seat | Project finance, joint venture, securitization | External counsel throughout, local counsel on entitlements |
| Engineering and integration house | Internal legal on corporate and contracts | Corporate, services agreements, licensing | Siting stays with the owner of the site |
What a general counsel told us about the reservation
A general counsel at a European colocation platform described the moment the capacity-adjustment rules landed as an accounting problem that turned into a legal one overnight. Her company held reserved megawatts across three plots, booked internally as an asset and presented to investors as pipeline. Nobody had been asked to say what evidence kept each of them alive, or which of the three would be surrendered first if the review went badly, and the answer was not in the connection file because nobody had ever needed to write it down. Separately, a head of legal at an industrial landlord converting warehouse holdings put the requisition problem more bluntly: the company had recruited a strong real-estate lawyer and then discovered that the file which decided the project was a prefectural one, so it hired well and instructed outward on the thing that moved.
When land is labeled before it is bought, the land lawyer changes job.
France did not respond to the queue by expanding it. It responded by identifying plots, pre-reserving capacity on them and running a competition for the result, which converts a private acquisition into something closer to an award.
On 7 May 2025 the Commission de régulation de l’énergie, the French energy regulator, approved an alternative connection procedure proposed by RTE for very-high-power consumption sites of 400 MW to 1 GW connecting at 400 kV, on plots previously identified by the State, with a horizon of 2028 to 2029. Thirteen days later RTE announced that at the State’s request it had pre-reserved 700 MW at Fouju and 700 MW at the site of the former Montereau power plant, both in Seine-et-Marne, for nine months extendable by three, while selection continued. In January 2026 the first contract under that procedure was signed for a campus at Fouju, with 240 MW to be delivered by the end of 2027 and 700 MW before the end of 2029.
The commercial terms sit in the convention model the regulator approved on 24 June 2025, and they read like project finance rather than like a utility contract. A candidate posts a bank guarantee equal to 10 percent of the extension-works cost; where a competition is run, every candidate posts it and the losers are released. Thirty percent of connection cost falls due on signature of the connection engagement. The connection convention itself is signed only once the building permit has been obtained and transmitted, with a further 60 percent due at that point and the balance at energization. A capacity charge of 20, 30 or 40 thousand euros per MW per year for six years, set by site according to the complexity of the reinforcement, prices the firm power made available during the ramp. Miss the permit deadline after formal notice and the project ends, and the reserved capacity goes back into the pool.
Read that sequence as a job description and the shape of the seat is obvious. The building permit is not a downstream administrative formality attached to a deal that has already closed. It is the condition on which the megawatts survive, and the person who owns the permit calendar is therefore the person who owns the capacity. A company that puts the connection under an energy adviser and the permit under a development team has divided one instrument between two functions that report to different people.
Not every project reaches that procedure, and the size distribution decides which ones do. On its 2026 figures page RTE reports that the majority of data center connection requests seek 100 to 200 MW, that about a dozen exceptional projects target more than 400 MW, and that a quarter of the projects are carried directly by large digital operators while the remainder are colocation. Set that against the 400 MW floor of the accelerated procedure and most campuses never see a State shortlist at all: they sit in the ordinary queue, competing on order of arrival. That is worth knowing before a legal department budgets for a process it will not be eligible to enter.
The labeled plots are also not empty fields. One of the two in Seine-et-Marne is the site of a decommissioned thermal power station, whose owner announced exclusive negotiations on 17 November 2025 to develop a high-power campus there. Outside the labeled set, an infrastructure fund and an operating company announced on 1 June 2026 a digital-infrastructure hub in Île-de-France targeting 500 MW. A siting lawyer in this market therefore spends more time on brownfield title, industrial legacy and demolition consents than the phrase grid-ready land suggests.
Two further mechanisms sit alongside it. Pooled reception zones let the operator oversize works in a defined area and split the cost among future users, and RTE expects that device to create about 1,200 MW of capacity in southern Île-de-France. And since 1 August 2025, under rules the regulator set on 18 December 2024 and Energy Code articles L. 342-22 to L. 342-24, an operator may reduce connection power where the power actually drawn is below the level subscribed: new installations are reassessed after five years or ramped over up to ten with at least three intermediate values, existing ones are recalculated on a five-year peak plus a 25 percent margin, and conventions signed on or after that date carry no indemnity at all.
| Instrument | French name | Issuer and date | What the legal department has to hold |
|---|---|---|---|
| Fast-track connection procedure | Procedure de raccordement fast track | CRE, deliberation n° 2025-120, 7 May 2025 | A connection engagement whose payment calendar starts before the permit exists |
| Connection convention model | Convention de raccordement | CRE, deliberation n° 2025-166, 24 June 2025 | A guarantee, a staged payment schedule and a permit condition that can release the capacity |
| Capacity adjustment | Evolution de la puissance de raccordement | CRE, deliberation n° 2024-229, live 1 August 2025 | Evidence that a reservation is being used, on a rolling review rather than at signature |
| Project of major national interest | Projet d'interet national majeur | Law n° 2026-403, 26 May 2026 | A prefectural permit file, a height derogation argument and the defense of the designation itself |
| Environmental authorization | Autorisation environnementale | Law n° 2023-320, 23 October 2023, clock from 22 October 2024 | A nine-month parallel file covering generators, water, species and public participation |
| Regional prefectural approval | Agrement | DRIEAT Ile-de-France, note of 1 June 2026 | A land, grid, heat, water and local-acceptance brief filed with the permit |
| Waste-heat and reporting duties | Chaleur fatale, arts. L. 236-1 to L. 236-3 | Energy Code, in force 1 October 2025 | A heat offtake contract with a municipality or network, not a sustainability commitment |
Land bought, then poweredLand labeled, then awarded
- Identify The State names plots with the land, the voltage and the local appetite to host a very large load. Nobody owns anything yet, and the criteria that decided the shortlist are public.
- Compete Candidates post the same guarantee and are selected against a published grid. What was once a negotiation with a landowner becomes a process with unsuccessful participants, and unsuccessful participants read reasons.
- Condition The winner signs an engagement, pays, and then has to produce a building permit before the connection contract exists. Everything downstream of the award is a planning file with money already spent against it.
The permit does not follow the connection contract in France. It precedes it, which makes the planning calendar the thing that decides whether the megawatts exist at all.
A campus here is measured against thresholds three orders of magnitude apart.
Most of the compliance surface has nothing to do with the connection product and everything to do with the building. It begins far below the megawatt scale of the grid conversation, and it begins earlier in the project than most schedules assume.
Concentration is why this region has an instrument of its own. Arcep’s annual survey of the sector, published on 21 May 2026 on 2024 data across 23 colocation operators and about 160 sites, put Île-de-France at 56 percent of surveyed sites and more than 70 percent of both maximum admissible IT power and electricity use. The statistical service of the ecological transition ministry reported on 2 July 2026 that 471 sites consuming more than one gigawatt-hour drew 4.3 TWh in 2024, of which Île-de-France accounted for 63 percent. Enedis reported separately on 16 June 2025 that data centers on its distribution network consumed 2.9 TWh in 2024 across nearly 400 mostly small and medium sites, while RTE recorded almost 1 TWh in 2025 on its own dedicated sites against 0.8 TWh in 2024. Three overlapping perimeters, one consistent finding: the load is here, the largest sites are migrating onto the transmission network, and the region legislates accordingly.
Île-de-France applies one instrument no other French metropolitan area applies. Construction, restructuring or extension of a data center above 5,000 m² of floor area requires a prefectural agrément under articles L. 510-1 and R. 510-6 of the Urban Code, and the decision must be attached to the building permit application. The regional environment and planning directorate reissued its guidance note on this on 1 June 2026, applying to filings from 1 July 2026, replacing a version dating from 2022. The criteria it sets out are land sobriety and a preference for previously developed sites, preservation of the grid through the shortest path to a 225 or 400 kV connection, cumulative effects on air, noise, heat and water, and the maturity of the dossier itself. Projects above 40 MW in the dense core attract heightened scrutiny, and the note sets a waste-heat recovery target of 20 percent of electrical energy there.
Behind the agrément sits the regional spatial plan approved by decree on 10 June 2025, which local planning documents must be made compatible with. Its orientations steer new data centers toward existing economic-activity sites, protect land with an industrial vocation from being displaced by them, and designate water-vigilance sectors that a cooling design has to answer for. The Institut Paris Region, which maintains the public observatory of the regional fleet, counted 213 data centers on 139 sites on 30 June 2026: 159 in operation, 21 under construction, 8 scheduled, 19 in instruction and 14 under study. That last column is the pipeline a siting lawyer is actually working in.
The environmental file runs on its own thresholds and its own clock. A data center is not itself a classified installation in French law; its generators, its fuel and its batteries are what pull the site into that regime. Under the combustion heading, a declaration covers one to under twenty megawatts of thermal power, registration covers twenty to under fifty, and full authorization begins at fifty, which is also the point at which an environmental impact assessment becomes systematic. Battery charging above six hundred kilowatts has its own heading. Separately, since 1 October 2025 the Energy Code has required reporting at 500 kW of installed IT power and waste-heat recovery at 1 MW unless a decree derogation applies, which converts a sustainability slide into a heat offtake contract with a municipality or a network operator.
The one thing that did get faster is the environmental authorization itself. The green industry law of 23 October 2023 cut the target from seventeen months to nine for complete files lodged from 22 October 2024, by running examination, consultation and public participation in parallel rather than in sequence. That is a genuine acceleration and it is also a trap: a parallel procedure punishes an incomplete dossier far more than a sequential one did, because there is no longer a quiet phase in which to fix it.
The duty that arrives first is measured in hundreds of kilowatts, and it arrives while the connection conversation is still being held in gigawatts.
Acceleration moved the decision. It did not move the objection.
Every instrument in the previous two sections compresses the front end of a project. The back end has been getting longer at the same time, and the cases that decide French campuses are turning on doctrine that predates the industry by decades.
The law of 26 May 2026 allows a data center to be designated a projet d’intérêt national majeur, a project of major national interest, under article L. 300-6-2 I bis of the Urban Code. The designation transfers the building permit from the mayor to the prefect, opens an accelerated route to making planning documents compatible, and creates a height derogation. It is a substantial change in who decides. It is not, however, a general exemption, and the Conseil constitutionnel said so five days before promulgation: in decision n° 2026-903 DC of 21 May 2026 it held at paragraph 30 that the designation does not carry an anticipated overriding public-interest ground for a protected-species derogation, because the relevant cross-reference points only to the original paragraph and not to the new one. The same decision struck the land-take provision from the article as a legislative rider. The same law, in the other direction, lets an authority refuse a permit for a data center where the water resource is structurally tight.
What that leaves is a project whose planning authority may have moved upward while its species file, its water file and its land-take arithmetic have not moved at all. A company reading the reform as a fast lane will discover the point at the worst moment, which is after the ecological survey season has closed.
The litigation record makes the same point from the other side. On 28 July 2026 an administrative court upheld the withdrawal of a building permit for a campus at Le Bourget, in Seine-Saint-Denis: the permit had been granted on 13 March 2026, two days before the first round of municipal elections, and withdrawn on 12 June 2026 by the incoming mayor. The court held the withdrawal was required because the building breached the local plan’s height rules. Not because of what the building was for. Because of how tall it was. Earlier, an appeal court had confirmed in an arrêt published on 8 October 2025 that adjoining halls at Wissous which could operate independently were not a single building requiring one permit, rejecting the argument that phasing had been used to avoid a fuller procedure.
Those two decisions are the practical brief. One says a project dies on an ordinary planning rule that any competent urbaniste would have flagged at concept stage. The other says a phasing strategy survives if it is genuinely a phasing strategy. Both were decided in ordinary administrative courts, on ordinary grounds, on timetables that do not accommodate a company still deciding who instructs. And the decree of 2 March 2026 that took underground lines out of the mandatory national debate has, if anything, raised the pressure: the consultation that used to happen in a national forum now has to be organized by the project itself, or it happens in a courtroom.
Knows the instrumentCan carry the position
- The external specialist Fluent in the connection procedure or in planning doctrine, rarely in both, and structurally unable to choose between two plots on the company’s behalf. Indispensable, and not a substitute for a decision-maker.
- The adjacent internal seat Real estate, construction or commercial counsel already inside the company, close enough to the project to be handed the file and without the administrative-procedure background it demands.
- The combined holder One lawyer who can keep a connection engagement and a permit calendar in the same head, instruct the litigator before the deadline rather than after it, and tell a development team which promise to stop making.
The requisition is the deliverable, and it is usually the problem.
We have worked the Paris in-house market for eight years, for operators, developers, industrial landlords and the funds behind them. What follows is our own record on this seat, including the part of it that does not flatter the method.
Sartori’s Paris mandate telemetry covers 19 closed in-house searches over the trailing three years, 93 percent of them completed, at a typical timeline of 4 to 7 months, with counter-offer incidence at 29 percent and a median of 15 working days between offer and signature. Within that set, 6 were seats that had to carry an energy or connection file and a land-use file at the same time. Those six behaved differently from the rest of the book: they did not fail more often, but they consistently sat at the long end of the timeline band rather than the short end, and in four of them the successful candidate came from a public-law or administrative background rather than from a corporate one.
The uncomfortable number sits in the same set. Three of those six ran past the seven-month upper bound of our own stated band, and two of the 19 closed Paris in-house searches did not complete at all. In two of the three that overran, the fault was at least as much ours as the client’s: we opened on a brief that named energy and real estate and left the administrative-litigation half of the job undefined, and a lawyer who will stand up at a tribunal administratif does not accept a seat whose authority to do so is unwritten. We now decline to open this search until the reporting line and the litigation authority are both written down, which costs a fortnight at the start and has repaid it every time.
There is a second limit worth stating. In the second-quarter 2026 survey wave drawn from the same Paris cohort, 38 of the 94 in-house respondents said their department had been asked, within the previous twelve months, to re-evidence a capacity reservation it had assumed was settled. That is a real and growing workload. It is also almost invisible in the public record, because it produces no filing, no announcement and no requisition — and because the response is usually to add the work to an existing lawyer rather than to open a seat. Our mapping across the Paris market covers roughly 9,000 lawyers, and this is one of the places where it sees the least.
Two engagements, anonymized
A colocation platform with plots in two departments of the outer ring came to us in early 2026 with a requisition for “juriste immobilier et énergie” and no reporting line. We spent three weeks converting that into a description of a seat that owned one connection engagement and two permit files, reported to the general counsel, held a defined external-counsel budget and could authorize a filing at a tribunal administratif without a committee. The search then ran five months from settled brief to signature. The successful candidate came out of a public-law practice rather than a real-estate one, and the deciding factor at offer stage was not the package but the fact that the seat carried the signature.
The second is the instructive failure. An industrial landlord converting logistics assets asked us for one lawyer covering grid connection, environmental authorization and the prefectural agrément across a portfolio. We told the head of legal it was two hires and opened anyway, on instruction. Ten weeks later we had two credible shortlists with no overlap and a candidate on each who would have taken half the job. The mandate closed as a public-law and environmental hire at six months, and the connection work went to an external panel. It is one of the two Paris in-house searches in the same three-year window where the brief had to be rewritten mid-process, and we should have declined the original scope instead of proving it wrong at the client’s expense.
Write the litigation authority before you write the job title.
Almost every failure mode in this search is decided before a candidate is approached. Either the requisition says which of the two files the seat owns and who it escalates to, or it does not, and no amount of sourcing repairs the difference.
| Factor | What to interrogate | Weighs most for |
|---|---|---|
| Sequence ownership | Has the candidate run a connection engagement and a permit file against each other, knowing which deadline forfeits the megawatts? | Every version of the seat |
| Prefectural filing | Have they assembled an Ile-de-France agrement dossier, or only advised on the criteria it applies? | Any campus above the floor-area threshold |
| Administrative litigation | Have they filed at a tribunal administratif on a deadline measured in days, as the named internal owner rather than as the person who forwarded the papers? | Sites in contested communes |
| Reservation discipline | Can they explain what evidence keeps a reservation alive under the adjustment rules, and what a commercial team must stop promising? | Portfolios with capacity held for future phases |
| Language and forum | Do they work in French with the prefecture and in English with a board, and are both fluent enough to carry a position? | Seats reporting into an international group |
| Reporting line | Does the seat report to the general counsel, or into a development function that will treat a filing deadline as a schedule item? | Structural, decided before the search opens |
A requisition that names two bodies of law and no authority produces a long search and a short tenure.
- Decide the escalation path first. Into the general counsel, or into a development function that will read a filing deadline as a schedule item. Candidates detect the answer in the first conversation.
- Say who may instruct a court filing. A seat that has to convene a committee before a deadline is not the seat you advertised, and the market knows the difference.
- Separate the sequence from the adjacent work. Compute contracting, construction and corporate matters are real and staffed elsewhere. One requisition covering everything produces two shortlists.
- Test for French administrative practice, not French language. Fluency is table stakes here; experience of a prefecture is the scarce half.
- Budget four to seven months, and start counting at the point the brief is settled rather than the point the requisition opens.
The question is not what the work is. It is who decides, and whether that will be you.
- Ask who signs the surrender. If a reservation has to be released, find out whose name goes on that decision before you find out what the package is.
- Ask what happened at the last hearing. A company that has already been to a tribunal administratif has a record and a habit. A company that has not is buying its first one.
- Own one full sequence, not one instrument. Engagement through permit through challenge, as the named internal holder. That is the credential this market prices, and volume of advice does not substitute for it.
- Keep the external relationship. A seat that directs excellent external counsel is a stronger platform than one that tries to replace them, and job descriptions describe both identically.
- Explore quietly. A confidential conversation commits nothing. See our guide on making the move in-house.
- Q1 Can one named person say what keeps each reservation alive? If the answer is spread across finance, development and an external adviser → the first hire is the person who consolidates it, not a litigator.
- Q2 Does the permit calendar and the connection calendar sit on one desk? If they sit in two functions → fix that before opening the search, because the hire will inherit the gap rather than close it.
- Q3 May the seat authorize a court filing without convening a committee? If not → you are advertising a coordinator and interviewing decision-makers, and they will decline.
- → All three clear? Open a targeted, confidential search — and keep the external panel, because this seat directs it rather than replacing it.
Common questions about hiring data center siting counsel in France
What does data center siting counsel France actually cover?
Two files on one clock: the grid connection and the permit that releases it. Since the fast-track connection procedure approved by the Commission de regulation de l'energie on 7 May 2025, a connection convention on a State-identified site is signed only after the building permit is obtained. The holder therefore owns the connection engagement, the payment calendar behind it, the prefectural agrement in Ile-de-France, the environmental authorization covering generators and water, and whatever challenge follows in the administrative courts. Splitting those between an energy adviser and a planning adviser is workable while nothing moves. It stops working the day a permit deadline decides whether the megawatts survive.
Why does Ile-de-France need a lawyer the rest of France does not?
One instrument: the prefectural agrement above 5,000 m² of floor area. The Direction regionale et interdepartementale de l'environnement, de l'amenagement et des transports reissued its guidance note on 1 June 2026, applying to filings from 1 July 2026, and it must be attached to the building permit application under Urban Code arts. L. 510-1 and R. 510-6. Projects above 40 MW in the dense core draw heightened scrutiny, and the note sets a 20 percent waste-heat recovery target there. No other French metropolitan area carries this filter, which is why a national energy specialist is not automatically qualified for a Paris campus.
How much power is actually available around Paris, and how much is being asked for?
770 MW of connection capacity already granted, against 6.5 GW requested. RTE's 2025 Electricity Review, published in April 2026, put dedicated-site data centers on the transmission system at 770 MW of connection capacity at the end of December 2025, individual sites running 40 to 240 MW, mainly in Ile-de-France. RTE's own figures page puts requested connection power in the region at 6.5 GW, close to the region's average load of about 7 GW, with roughly 7 GW held in reserve. Those three numbers measure capacity granted, volume asked for and volume held.
Can outside counsel hold this instead of an internal hire?
Outside counsel files the dossier; only the company can forfeit the capacity. A Paris firm can draft the environmental authorization and appear at the tribunal administratif. It cannot decide whether to sign an engagement that commits 30 percent of connection cost before a permit exists, whether to defend a reservation under the capacity-adjustment rules live since 1 August 2025 or release it, or which of two plots to abandon when a municipal opinion turns. Every operator requisition read for this article names the direction of external counsel as a duty of the internal seat rather than an alternative to it.
What is the realistic timetable to fill this seat, and what goes wrong?
Budget 4 to 7 months and expect the requisition, not the market, to be the obstacle. Across the 19 in-house searches Sartori closed in Paris over the trailing three years, 93 percent completed, counter-offer incidence ran at 29 percent and the median gap between offer and signature was 15 working days. The recurring failure is a job description that names droit de l'energie and droit de l'urbanisme in one line and then reports into a development function with no authority to stop a filing. Two candidate pools answer that advertisement, and neither one takes it.
Does the new projet d'interet national majeur status make siting easier?
It moves the permit, not the risk. Law n° 2026-403 of 26 May 2026 lets a data center be designated a projet d'interet national majeur, which transfers the building permit to the prefect and opens a height derogation. On 21 May 2026 the Conseil constitutionnel held at paragraph 30 that the designation carries no anticipated overriding-interest ground for a protected-species derogation, and struck the land-take provision as a rider. The same law also lets an authority refuse a permit where water resource is structurally tight. Acceleration relocated the decision; the species file and the water file are unchanged.
The statute, the grid review and the prefectural note behind these figures.
Grid figures come from the transmission operator's own review and figures pages. Procedural terms come from the regulator's deliberations. Land-use criteria come from the regional directorate's guidance and the regional plan. Court outcomes come from the courts' own publications and from agency reporting.
Sources & further reading
37 references- Sartori & Partners — Paris Legal Talent Research Programme (250 structured interviews; ~9,000 lawyers mapped; quarterly surveys since 2019; mandate telemetry) sartoriglobal.com ↗
- RTE — 2025 Electricity Review, full report (April 2026); connection capacity, utilization and access rights assets.rte-france.com ↗
- RTE — Les data centers en chiffres clés (2026): requested and reserved power by region rte-france.com ↗
- CRE — Approval of the fast-track connection procedure for very-high-power consumption sites (7 May 2025) cre.fr ↗
- CRE — Délibération n° 2025-120 of 7 May 2025, fast-track connection procedure (full text) cre.fr ↗
- CRE — Approval of the fast-track connection convention model (27 June 2025) cre.fr ↗
- CRE — Délibération n° 2025-166 of 24 June 2025, connection convention model (full text) cre.fr ↗
- CRE — Modalities for adjusting connection power for consumption installations (20 December 2024) cre.fr ↗
- CRE — Délibération n° 2024-229 of 18 December 2024, connection-power adjustment and indemnification cre.fr ↗
- RTE Services — Publication of the fast-track procedure (9 May 2025) services-rte.com ↗
- RTE Services — Pre-reservation of capacity on four suitable sites (20 May 2025) services-rte.com ↗
- RTE Services — Mapping of consumption pooling areas (16 December 2024) services-rte.com ↗
- RTE — First fast-track connection contract signed for a digital-infrastructure campus (26 January 2026) rte-france.com ↗
- DRIEAT Île-de-France — Fiche repère on agrément applications for data centers (1 June 2026) drieat.ile-de-france.developpement-durable.gouv.fr ↗
- DRIEAT Île-de-France — Agrément for business premises, procedure page drieat.ile-de-france.developpement-durable.gouv.fr ↗
- Région Île-de-France — SDRIF-E, regional spatial plan approved by decree of 10 June 2025 iledefrance.fr ↗
- Région Île-de-France — Regional data center strategy (26 June 2026) iledefrance.fr ↗
- Institut Paris Region — Observatory of data centers in Île-de-France (30 June 2026) institutparisregion.fr ↗
- Legifrance — Law n° 2026-403 of 26 May 2026 on the simplification of economic life legifrance.gouv.fr ↗
- Conseil constitutionnel — Decision n° 2026-903 DC of 21 May 2026 conseil-constitutionnel.fr ↗
- Legifrance — Energy Code, arts. L. 236-1 to L. 236-3 (data center reporting and waste-heat recovery) legifrance.gouv.fr ↗
- Legifrance — Decree n° 2026-146 of 2 March 2026 (public debate and environmental assessment) legifrance.gouv.fr ↗
- Direction générale des Entreprises — Guide to siting a data center in France (November 2025) entreprises.gouv.fr ↗
- MRAe Île-de-France — Éclairages: data centers and environmental assessment (2023) mrae.developpement-durable.gouv.fr ↗
- Cour administrative d'appel de Versailles — Wissous data center extension, arrêt 23VE02040 (8 October 2025) versailles.cour-administrative-appel.fr ↗
- Le Figaro / AFP — Court upholds the withdrawal of a data center building permit at Le Bourget (28 July 2026) lefigaro.fr ↗
- Arcep — Annual survey for sustainable digital technology, 2026 edition (21 May 2026, 2024 data) arcep.fr ↗
- SDES — Electricity consumption of data centers in 2024 (2 July 2026) statistiques.developpement-durable.gouv.fr ↗
- Enedis — Data center consumption on the distribution network (16 June 2025) enedis.fr ↗
- EY and France Datacenter — Baromètre 2025, installed capacity by market (June 2025) francedatacenter.com ↗
- EDF — High-power data center on the site of a former thermal plant, wider Paris region (17 November 2025) edf.fr ↗
- Ardian — Digital-infrastructure hub announced in Île-de-France (1 June 2026) ardian.com ↗
- Employer posting — Legal counsel, real estate and infrastructure, Paris (advertised 7 March 2026) themuse.com ↗
- Employer posting — Senior compute legal counsel, Paris (advertised 28 June 2026) lawprofiler.com ↗
- Employer posting — Transmission operator legal department, network-access pole, Paris region (recruitment profile, 2026) welcometothejungle.com ↗
- Employer posting — Juriste, corporate and contracts, data center engineering house, Montrouge (advertised December 2025) welcometothejungle.com ↗
- Sartori & Partners — In-house counsel recruiting ↗
Power figures on this page measure four different things: connection capacity granted on the transmission system, installed colocation IT capacity in the Paris market, connection power requested, and connection capacity reserved. The comparison drawn between granted capacity and requested power in the opening section is this article's own arithmetic on two published figures, not a ratio the transmission operator publishes. Threshold figures are published floors, not counts of sites that meet them. The regional guidance note of June 2026 is an instruction document rather than a regulation, and how far it binds is contested among French practitioners. Requisition content is what an employer published on a single posting; French postings in this market do not disclose base compensation, so no compensation range is shown.
Our own figures — the interview cohort, the mandate telemetry, the counter-offer incidence and the offer-to-acceptance window — come from the continuous research program described on our research page, which sets out the cohorts, the survey waves and the mapping coverage behind every Sartori number quoted above.
Adjacent maps for the same buyer.
This seat sits between the infrastructure finance market it competes with for candidates and the structural work of building a corporate legal department. These pieces extend the map without repeating the argument above.
Hiring Your First General Counsel
The structural questions that decide whether a first senior legal hire works: scope, reporting line, budget authority and the work the seat will actually own.
Read the hiring guideInfrastructure & Project Finance
The wider infrastructure legal market this seat competes with for the same candidates, and how sponsors staff the finance side of a campus.
See the sector pageIn-House Counsel Recruiting
How we build corporate legal departments: scoping the seat before the search, mapping quietly, and telling a company when a requisition is not ready.
See how we workA quiet conversation
Deciding whether to build the seat or keep instructing outward?
We build corporate legal departments in Paris, and we are as willing to tell a company that a requisition is not ready as to open a search. Confidential, no obligation.